NOTICE
PUBLIC INFORMATION MEETING
related to
2021 ROAD RECONSTRUCTION and UTILITY IMPROVEMENT
PROJECT
The Village of Genoa City has scheduled a Public Information Meeting (PIM) to present information regarding the 2021 Road Reconstruction and Utility Improvement project.
This meeting will be held:
WEDNESDAY, APRIL 14th, 2021
at
Village Hall Board Room
755 Fellows Rd
Genoa City, WI 53128
4:00 pm to 7:00 pm
This is an opportunity for you to ask questions and offer comments regarding the proposed improvements. Exhibits and plans of the project will be on display. This is an open house meeting and not a public hearing. We have attempted to notify all interested parties, but would appreciate your assistance by informing others who may be interested in attending this meeting. The Village Hall's Board Room is wheelchair accessible.
The project is tentatively scheduled for June through September 2021. Streets will remain open to local traffic at all times. Access to properties may be restricted during construction-notice will be given prior to driveway closures.
The Villages may be requesting temporary easements from some property owners in order to construct the improvements through this narrow corridor. Also, all flower beds and ornamentals within the Village right-of-way will need to be removed prior to construction.
If you have questions regarding this project or would like additional information, please contact John Cole, Village Superintendent at (262) 949-5583 or Brandon Foss, Village Engineer at (262) 317-3374.
We look forward to meeting with you on April 14th, 2021.
SUMMARY OF WORK
2021 ROAD RECONSTRUCTION and UTILITY IMPROVEMENT PROJECT
This project includes work on the following streets/locations:
- North Freeman Street, between the Franklin St. and Darling Rd;
- Sumner Court, between First St. and Main St.;
- First Street (sidewalk only), between Freeman St. and S. Wisconsin St.;
- Library Parking Lot repave
The following general work will be completed:
For North Freeman Street:
- Reconstruct street including new concrete curb.
- New concrete driveway aprons.
- Spot repair the existing sanitary sewer main.
- Replace the existing 4" water main with 8" PVC water main, including hydrants and service valves.
- Replace existing 6" sewer force main with new HPDE pipe.
- Various sidewalk replacement due to cracks, grade adjustment, and new water services.
For Sumner Court
- Reconstruct street including new concrete curb.
- New concrete driveway aprons.
- Replace existing shallow water main with new 8" PVC, including hydrants and service valves.
- Install liner in the existing clay sanitary sewer.
- Install new 5-foot wide sidewalk on both the east and west sides of the street.
For First Street
- Install new 4-foot wide sidewalk on the north side of the street only.
For the Library Parking Lot
- The existing asphalt parking lot will be repaved.